Project Details
Project Type
Environmental clean and encapsulation
Client
Nationwide Electricity Provider
Services Utilised
Asbestos encapsulation and Environmental Clean
Timeline
October – December 2020
Project Description

Cake Commercial Services was awarded the project to clean and encapsulate a contaminated cable basement of a substation. The safest methodology, involved a significant amount of concrete being poured into cable trenches to encapsulate asbestos related dust, whilst protecting the cables for possible fire risk, and enabling safe working platforms within the cable basement, removing trip hazards. A detailed environmental clean of the above ground cables and trays, along with cleaning all surfaces within the basement, to provide an Asbestos free working environment for ongoing maintenance and future upgrades. All work completed under Class A conditions